| |

Erosion gully caused by Trapper’s Dam spillway. PHOTO: DARREN LARCOMBE |
Solving an erosion problem – the fate of Trapper’s Dam
A success story from Carnarvon
Station Reserve Manager Darren Larcombe
It is usually years, or even decades,
before the results of conservation work
can be seen in real improvements on the
ground. As reserve managers, we are
used to being patient and watching and
monitoring the land for years before we
see the fruits of our labours. So achieving
a major conservation goal at Carnarvon
Station Reserve in the space of a few
weeks was really inspiring. We resolved
a major soil erosion problem and restored
the natural flow of water from Gorge
Gully to the Channin Creek.
|
|
 |
|





 |
 |
Carnarvon Station Reserve in central
Queensland was purchased by Bush
Heritage and its supporters in 2001.This 59 000 hectare reserve protects
endangered bluegrass grasslands
and formerly unreserved poplar box
woodlands. The reserve management
plan identified soil erosion caused by
historical pastoral activities, a poorly
constructed spillway on the main dam,
and siting of roads, as one of the
key threats to these ecosystems. We
began managing soil erosion as soon
as we took possession of the reserve.
Removing the cattle significantly reduced
the grazing pressure, which had been a
major contributor to the problem.
Trapper’s Dam in Gorge Gully was a
significant problem. Built during the
mid-1980s as a stock watering point,
it not only held a large volume of water
that rightly belonged in the Channin
Creek system but also had an incomplete
spillway that had caused any overflow
of water to cut an erosion scar 22 metres
wide along the drainage line. The scar
stretched for 280 metres and ranged
in depth from two to ten metres; it was
a very big hole! As a conservative
estimate, that hole equated to the loss
of about 37 000 cubic metres of soil. With no
remedial action, this landscape with
its endangered vegetation community
would continue to deteriorate as the
erosion proceeded to undermine the
adjacent alluvial plain. Our goal was to
prevent further soil loss and halt the
destabilisation of the fringing areas.
Planning for the rehabilitation of the
site began in 2005. We commissioned
an environmental engineer from the
University of Melbourne to do a site
survey, and sought the advice of local
earth-moving contractors. Getting advice
about removing the dam proved difficult.
We kept getting the same response: ‘You want to do what?!!’ Far more
seemed to be known about building
dams than about removing them.
A number of options were explored but
the best and permanent solution involved
breaching the dam wall and returning
the water to the creek. That involved
moving approximately 100 000 tonnes
of earth. The Queensland Government
assisted with funding from the
Biodiversity Incentives Tender, and
the Southwest Natural Resource
Management contributed through the
Nature Assist Program.
Expert staff and volunteers were
recruited and a D8 bulldozer was booked
for the month of October 2007. The
dam had dried out due to the prolonged
drought and we hoped that the parched
conditions would continue for just a bit
longer. Our National Operations Officer
Glen Norris used his dozer skills to
remove a 240 metre section of dam
wall. He used the soil to fill and repair
the eroded spillway and construct new
contour banks. Expert volunteer John
Hansen then took over and used the
remaining soil to reshape the surrounding
country. Using the tractor, the reserve
staff then cut furrows into the contour
banks to prevent further erosion and
in preparation for sowing. We spread
native grass seed harvested earlier in the
season from other areas of the property.
The recent heavy rains were the ultimate
test of the success of the project. A
torrential 900 mm of rain has fallen on
the site in the three months since the
work was completed. The old dam site
now channels water into Channin Creek,
which forms the headwaters of the
Warrego River, a major feeder system for
the Murray–Darling catchment. Our newly
formed and vegetated contour banks held
up under the strain and have significantly
lessened the silt load flowing into an
already stressed river system.
This has been the first soil conservation
project of this type undertaken by
Bush Heritage on any of its reserves. It
required 620 hours of staff and volunteer
time. We extend special thanks to Rob
Argent for his technical advice, to Glen
Norris for his work on the dozer and
for imparting his practical knowledge of
earthworks, and to John Hansen for his
extraordinary skills in earth-moving. Peter
and Margaret Calder did a wonderful job
collecting the grass seed required for
the revegetation work, using the grass
seed harvester generously donated by
the Andyinc Foundation. Finally, ‘thank
you’ to our team of ‘chook-feeders’ for
spending a hot afternoon spreading seed.
Without your efforts, the contour banks
would have washed away in the first
heavy rains.
Now we have a newly constructed
native grassland that is green and lush
and doing its job of holding the soil and
helping to further stabilise this once-degraded
area. |
| |
| From top: Seed harvester cutting seed from the reserve. Soil from the dam wall is used to fill the gully. Bush Heritage ecologist Murray Haseler casts the first handful of native grass seed. Bush Heritage staff and volunteers spreading seed. Early stages of regeneration. Our new native grassland on the old
dam site. PHOTOS: DARREN LARCOMBE AND GLEN NORRIS |
| |
 |
 |
| Giant water-holding frog. Pale field rat. PHOTOS: SANDY WALTERS |
Rain pays dividends at
Carnarvon Station Reserve
Following the recent rain, the
Carnarvon grasslands are producing
a bumper crop of native seed and
teeming with invertebrates. As we set
out to do the next monitoring round
we wondered whether this might
produce some interesting animals.
It did! So far, our pitfall traps have
revealed two new species for the
reserve, the pale field rat and the giant
water-holding frog. It’s great to see these
species making a comeback.
|
|
|